BREAKDOWN OF UNIT PRICE
Item: (A08D6) Form Work for RCC Work-Substruc
Basis:100 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work-Substructure
100.000
sft
40.00
4000.00
Sub-Total(L1)
4000.00
430.56
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
100.000
sft
35.00
3500.00
Sub-Total(M1)
3500.00
376.74
Total(1)
807.30
Add over head on Total(1)
5.0 %
40.37
Total(2)
847.67
Add Profit on Total(2)
10.0 %
84.77
Total(3)
932.43
Add VAT on Unit Price
5.5 %
57.30
Add Income Tax on Unit Price
5.0 %
52.09
Unit Price
1041.82
Say
1042
per M2