BREAKDOWN OF UNIT PRICE
Item: (A08CW) RCC(1:1.5:3) Form,Sylht-StairBase
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
22.000
bag
535.00
11770.00
Sand - Sylhet
43.000
cft
65.00
2795.00
Stone-chips-19mm
86.000
cft
190.00
16340.00
Sub-Total(A1)
30905.00
10914.10
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Form work-Substructure
80.000
sft
40.00
3200.00
Sub-Total(L1)
7200.00
2542.68
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel shutter-New
80.000
sft
30.00
2400.00
Sub-Total(M1)
2400.00
847.56
Total(1)
14304.34
Add over head on Total(1)
5.0 %
715.22
Total(2)
15019.56
Add Profit on Total(2)
10.0 %
1501.96
Total(3)
16521.51
Add VAT on Unit Price
5.5 %
1015.29
Add Income Tax on Unit Price
5.0 %
922.99
Unit Price
18459.79
Say
18460
per CUM