BREAKDOWN OF UNIT PRICE
Item: (A08CV) RCC(1:1.5:3) Form,Sylhe-tLif Base
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
22.000
bag
535.00
11770.00
Sand - Sylhet
43.000
cft
65.00
2795.00
Stone-chips-19mm
86.000
cft
190.00
16340.00
Sub-Total(A1)
30905.00
10914.10
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Form work-Substructure
100.000
sft
40.00
4000.00
Sub-Total(L1)
8000.00
2825.20
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel shutter-New
100.000
sft
30.00
3000.00
Sub-Total(M1)
3000.00
1059.45
Total(1)
14940.01
Add over head on Total(1)
5.0 %
747.00
Total(2)
15687.01
Add Profit on Total(2)
10.0 %
1568.70
Total(3)
17255.71
Add VAT on Unit Price
5.5 %
1060.41
Add Income Tax on Unit Price
5.0 %
964.01
Unit Price
19280.13
Say
19280
per CUM