BREAKDOWN OF UNIT PRICE
Item: (A08CS) RCC(1:2:4) Form,Brick,L:S=1:1Lntl
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
22.500
cft
35.00
787.50
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
22.500
cft
65.00
1462.50
Brick-chips-20mm
90.000
cft
175.00
15750.00
Sub-Total(A1)
27630.00
9757.53
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC work Super-structure
100.000
cft
40.00
4000.00
Form work Super-structure
457.200
sft
35.00
16002.00
Sub-Total(L1)
20002.00
7063.71
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
457.200
sft
35.00
16002.00
Sub-Total(M1)
16002.00
5651.11
Total(1)
22613.61
Add over head on Total(1)
5.0 %
1130.68
Total(2)
23744.29
Add Profit on Total(2)
10.0 %
2374.43
Total(3)
26118.72
Add VAT on Unit Price
5.5 %
1605.06
Add Income Tax on Unit Price
5.0 %
1459.15
Unit Price
29182.92
Say
29183
per CUM