BREAKDOWN OF UNIT PRICE
Item: (A08CQ) RCC(1:2:4) Form,Loc:Syl=1:1Column
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
22.500
cft
35.00
787.50
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
22.500
cft
65.00
1462.50
Stone-chips-19mm
90.000
cft
190.00
17100.00
Sub-Total(A1)
28980.00
10234.29
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC work Super-structure
100.000
cft
40.00
4000.00
Form work Super-structure
262.128
sft
35.00
9174.48
Sub-Total(L1)
13174.48
4652.57
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
262.128
sft
35.00
9174.48
Sub-Total(M1)
9174.48
3239.97
Total(1)
18268.08
Add over head on Total(1)
5.0 %
913.40
Total(2)
19181.49
Add Profit on Total(2)
10.0 %
1918.15
Total(3)
21099.63
Add VAT on Unit Price
5.5 %
1296.63
Add Income Tax on Unit Price
5.0 %
1178.75
Unit Price
23575.01
Say
23575
per CUM