BREAKDOWN OF UNIT PRICE
Item: (A08CP) RCC(1:2:4) Form, Sylhet-Padestal
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
22.500
cft
35.00
787.50
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
22.500
cft
65.00
1462.50
Stone-chips-19mm
90.000
cft
190.00
17100.00
Sub-Total(A1)
28980.00
10234.29
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Form work-Substructure
262.128
sft
40.00
10485.12
Sub-Total(L1)
14485.12
5115.42
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
262.128
sft
35.00
9174.48
Sub-Total(M1)
9174.48
3239.97
Total(1)
18730.93
Add over head on Total(1)
5.0 %
936.55
Total(2)
19667.48
Add Profit on Total(2)
10.0 %
1966.75
Total(3)
21634.23
Add VAT on Unit Price
5.5 %
1329.48
Add Income Tax on Unit Price
5.0 %
1208.62
Unit Price
24172.32
Say
24172
per CUM