BREAKDOWN OF UNIT PRICE
Item: (A08CH) RCC(1:2:4) Brickchp, L:S=1:1-Supe
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
22.500
cft
35.00
787.50
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
22.500
cft
65.00
1462.50
Brick-chips-20mm
90.000
cft
175.00
15750.00
Sub-Total(A1)
27630.00
9757.53
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC work Super-structure
100.000
cft
40.00
4000.00
Sub-Total(L1)
4000.00
1412.60
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 80 times
1.000
set
120.00
120.00
Sub-Total(M1)
120.00
42.38
Total(1)
11353.77
Add over head on Total(1)
5.0 %
567.69
Total(2)
11921.46
Add Profit on Total(2)
10.0 %
1192.15
Total(3)
13113.61
Add VAT on Unit Price
5.5 %
805.86
Add Income Tax on Unit Price
5.0 %
732.60
Unit Price
14652.08
Say
14652
per CUM