Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (A08C3) RCC(1:2:4)-Form,Syl,Brick-GF Slab
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
45.000
cft
65.00
2925.00
Brick-chips-20mm
90.000
cft
175.00
15750.00
Sub-Total(A1)
28305.00
9995.91
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Form work-Substructure
3.353
sft
40.00
134.12
Sub-Total(L1)
4134.12
1459.96
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
3.353
sft
35.00
117.36
Sub-Total(M1)
117.36
41.44
Total(1)
11638.58
Add over head on Total(1)
5.0 %
581.93
Total(2)
12220.51
Add Profit on Total(2)
10.0 %
1222.05
Total(3)
13442.56
Add VAT on Unit Price
5.5 %
826.08
Add Income Tax on Unit Price
5.0 %
750.98
Unit Price
15019.62
Say
15020
per cum