BREAKDOWN OF UNIT PRICE
Item: (A08BW) RCC(1:1.5:3) L:S=1:2, Brick-SubSt
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
14.620
cft
35.00
511.70
Cement
22.000
bag
535.00
11770.00
Sand - Sylhet
28.380
cft
65.00
1844.70
Brick-chips-20mm
86.000
cft
175.00
15050.00
Sub-Total(A1)
29176.40
10303.65
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Sub-Total(L1)
4000.00
1412.60
Total(1)
11857.51
Add over head on Total(1)
5.0 %
592.88
Total(2)
12450.38
Add Profit on Total(2)
10.0 %
1245.04
Total(3)
13695.42
Add VAT on Unit Price
5.5 %
841.62
Add Income Tax on Unit Price
5.0 %
765.11
Unit Price
15302.14
Say
15302
per CUM