BREAKDOWN OF UNIT PRICE
Item: (A08BV) RCC(1:2:4) Form, Sylhet, Slab
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
45.000
cft
65.00
2925.00
Stone-chips-19mm
90.000
cft
190.00
17100.00
Sub-Total(A1)
29655.00
10472.66
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC work Super-structure
100.000
cft
40.00
4000.00
Form work Super-structure
202.303
sft
35.00
7080.61
Sub-Total(L1)
11080.61
3913.12
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
202.303
sft
35.00
7080.61
Sub-Total(M1)
7080.61
2500.52
Total(1)
17027.55
Add over head on Total(1)
5.0 %
851.38
Total(2)
17878.93
Add Profit on Total(2)
10.0 %
1787.89
Total(3)
19666.83
Add VAT on Unit Price
5.5 %
1208.58
Add Income Tax on Unit Price
5.0 %
1098.71
Unit Price
21974.11
Say
21974
per CUM