BREAKDOWN OF UNIT PRICE
Item: (A08BK) RCC(1:2:4) Form-BrickChip-Lintel
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
22.500
cft
35.00
787.50
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
22.500
cft
65.00
1462.50
Brick-chips-20mm
90.000
cft
175.00
15750.00
Sub-Total(A1)
27630.00
9757.53
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC work Super-structure
100.000
cft
40.00
4000.00
Form work Super-structure
476.000
sft
35.00
16660.00
Sub-Total(L1)
20660.00
7296.08
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
476.000
sft
35.00
16660.00
Sub-Total(M1)
16660.00
5883.48
Total(1)
23078.35
Add over head on Total(1)
5.0 %
1153.92
Total(2)
24232.27
Add Profit on Total(2)
10.0 %
2423.23
Total(3)
26655.50
Add VAT on Unit Price
5.5 %
1638.05
Add Income Tax on Unit Price
5.0 %
1489.13
Unit Price
29782.68
Say
29783
per CUM