BREAKDOWN OF UNIT PRICE
Item: (A08B1) Ready-mix Concrete-3500 psi-Pile
Basis:239 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel
30.000
Ltr
70.00
2100.00
Tyre Crane-10 ton-12 hr
1.000
day
10000.00
10000.00
Sub-Total(E1)
12100.00
1787.91
Total(1)
1787.91
Add over head on Total(1)
5.0 %
89.40
Total(2)
1877.31
Add Profit on Total(2)
10.0 %
187.73
Total(3)
2065.04
Add VAT on Unit Price
5.5 %
126.90
Add Income Tax on Unit Price
5.0 %
115.37
Unit Price
2307.31
Say
2307
per M3