BREAKDOWN OF UNIT PRICE
Item: (A08AT) Form Work-Steel-Round
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
75.000
kg
260.00
19500.00
Sub-Total(A1)
19500.00
2098.98
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 80 times
1.000
set
120.00
120.00
Turn Buckle-use 50 time
8.000
no.
12.00
96.00
Steel Round Shutter
100.000
sft
100.00
10000.00
Steel Props-use 50 time
8.000
no.
50.00
400.00
Pea-Cone
8.000
no.
225.00
1800.00
Tie Rod
8.000
no.
75.00
600.00
MS Nuts
100.000
pcs
5.00
500.00
Shutter Grinding and Oili
100.000
sft
10.00
1000.00
MS Box-100x100 use 40 tim
80.000
rft
7.50
600.00
Sub-Total(M1)
15116.00
1627.09
Total(1)
3726.07
Add over head on Total(1)
5.0 %
186.30
Total(2)
3912.37
Add Profit on Total(2)
10.0 %
391.24
Total(3)
4303.61
Add VAT on Unit Price
5.5 %
264.47
Add Income Tax on Unit Price
5.0 %
240.42
Unit Price
4808.50
Say
4808
per M2