BREAKDOWN OF UNIT PRICE
Item: (A08AN) Concrete C30 in Padestal
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
25.000
bag
535.00
13375.00
Sand - Sylhet
43.000
cft
65.00
2795.00
Stone-chips-19mm
86.000
cft
190.00
16340.00
Sub-Total(A1)
32510.00
11480.91
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Sub-Total(L1)
4000.00
1412.60
Total(1)
13034.77
Add over head on Total(1)
5.0 %
651.74
Total(2)
13686.50
Add Profit on Total(2)
10.0 %
1368.65
Total(3)
15055.16
Add VAT on Unit Price
5.5 %
925.18
Add Income Tax on Unit Price
5.0 %
841.07
Unit Price
16821.40
Say
16821
per M3