BREAKDOWN OF UNIT PRICE
Item: (A08AK) Form Work-Overhead Drain
Basis:100 sft
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 80 times
1.000
set
120.00
120.00
Steel Props-use 50 time
2.000
no.
50.00
100.00
MS Pipe-50 mm
2.000
rft
20.00
40.00
Over Head Drain Shutter
100.000
sft
60.00
6000.00
Shutter Grinding and Oili
100.000
sft
10.00
1000.00
Sub-Total(M1)
7260.00
781.47
Total(1)
781.47
Add over head on Total(1)
5.0 %
39.07
Total(2)
820.54
Add Profit on Total(2)
10.0 %
82.05
Total(3)
902.59
Add VAT on Unit Price
5.5 %
55.47
Add Income Tax on Unit Price
5.0 %
50.42
Unit Price
1008.48
Say
1008
per M2