BREAKDOWN OF UNIT PRICE
Item: (A08A4) Form Work-Steel-Tie/ Lintel
Basis:100 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work Super-structure
100.000
sft
35.00
3500.00
Sub-Total(L1)
3500.00
376.74
Total(1)
376.74
Add over head on Total(1)
5.0 %
18.84
Total(2)
395.58
Add Profit on Total(2)
10.0 %
39.56
Total(3)
435.13
Add VAT on Unit Price
5.5 %
26.74
Add Income Tax on Unit Price
5.0 %
24.31
Unit Price
486.18
Say
486
per M2