BREAKDOWN OF UNIT PRICE
Item: (A08A3) Form Work-Steel- upto Plinth
Basis:100 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work-Substructure
100.000
sft
40.00
4000.00
Sub-Total(L1)
4000.00
430.56
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Shuttter-Pilinth
100.000
sft
40.00
4000.00
Sub-Total(M1)
4000.00
430.56
Total(1)
861.12
Add over head on Total(1)
5.0 %
43.06
Total(2)
904.18
Add Profit on Total(2)
10.0 %
90.42
Total(3)
994.59
Add VAT on Unit Price
5.5 %
61.12
Add Income Tax on Unit Price
5.0 %
55.56
Unit Price
1111.28
Say
1111
per M2