BREAKDOWN OF UNIT PRICE
Item: (A05F5) Earth Compaction
Basis:100 sft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.070
day
15000.00
1050.00
Sub-Total(E1)
1050.00
113.02
Total(1)
113.02
Add over head on Total(1)
5.0 %
5.65
Total(2)
118.67
Add Profit on Total(2)
10.0 %
11.87
Total(3)
130.54
Add VAT on Unit Price
5.5 %
8.02
Add Income Tax on Unit Price
5.0 %
7.29
Unit Price
145.86
Say
146
per m2