BREAKDOWN OF UNIT PRICE
Item: (A05F4) Filling-Earthwith Roller
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.070
day
15000.00
1050.00
Sub-Total(E1)
1050.00
370.81
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling
100.000
cft
6.00
600.00
Sub-Total(L1)
600.00
211.89
Total(1)
582.70
Add over head on Total(1)
5.0 %
29.13
Total(2)
611.83
Add Profit on Total(2)
10.0 %
61.18
Total(3)
673.02
Add VAT on Unit Price
5.5 %
41.36
Add Income Tax on Unit Price
5.0 %
37.60
Unit Price
751.97
Say
752
per M3