BREAKDOWN OF UNIT PRICE
Item: (A05CL) Filter Layer-Pick Jhama-Chip-40mm
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pick Jhama Chips-40mm
120.000
cft
90.00
10800.00
Sub-Total(A1)
10800.00
3814.02
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.070
day
15000.00
1050.00
Sub-Total(E1)
1050.00
370.81
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sub-base Work/Gravel fiil
100.000
cft
20.00
2000.00
Sub-Total(L1)
2000.00
706.30
Total(1)
4891.13
Add over head on Total(1)
5.0 %
244.56
Total(2)
5135.68
Add Profit on Total(2)
10.0 %
513.57
Total(3)
5649.25
Add VAT on Unit Price
5.5 %
347.16
Add Income Tax on Unit Price
5.0 %
315.60
Unit Price
6312.01
Say
6312
per m3