BREAKDOWN OF UNIT PRICE
Item: (A05CG) Filling-Gravel
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.140
day
15000.00
2100.00
Sub-Total(E1)
2100.00
741.62
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sub-base Work/Gravel fiil
100.000
cft
20.00
2000.00
Sub-Total(L1)
2000.00
706.30
Total(1)
1447.92
Add over head on Total(1)
5.0 %
72.40
Total(2)
1520.31
Add Profit on Total(2)
10.0 %
152.03
Total(3)
1672.34
Add VAT on Unit Price
5.5 %
102.77
Add Income Tax on Unit Price
5.0 %
93.43
Unit Price
1868.54
Say
1869
per M3