BREAKDOWN OF UNIT PRICE
Item: (A05CF) Filling-Crushed Stone
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone-chips-19mm
130.000
cft
190.00
24700.00
Sub-Total(A1)
24700.00
8722.81
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.140
day
15000.00
2100.00
Sub-Total(E1)
2100.00
741.62
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sub-base Work/Gravel fiil
100.000
cft
20.00
2000.00
Sub-Total(L1)
2000.00
706.30
Total(1)
10170.72
Add over head on Total(1)
5.0 %
508.54
Total(2)
10679.26
Add Profit on Total(2)
10.0 %
1067.93
Total(3)
11747.18
Add VAT on Unit Price
5.5 %
721.89
Add Income Tax on Unit Price
5.0 %
656.27
Unit Price
13125.34
Say
13125
per M3