BREAKDOWN OF UNIT PRICE
Item: (A05A7) Filling-Coars Sand(2.5) by Roller
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Sylhet
120.000
cft
65.00
7800.00
Sub-Total(A1)
7800.00
2754.57
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.140
day
15000.00
2100.00
Sub-Total(E1)
2100.00
741.62
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling
100.000
cft
6.00
600.00
Sub-Total(L1)
600.00
211.89
Total(1)
3708.08
Add over head on Total(1)
5.0 %
185.40
Total(2)
3893.48
Add Profit on Total(2)
10.0 %
389.35
Total(3)
4282.83
Add VAT on Unit Price
5.5 %
263.19
Add Income Tax on Unit Price
5.0 %
239.26
Unit Price
4785.28
Say
4785
per CUM