BREAKDOWN OF UNIT PRICE
Item: (A03P1) Brick on Edging1
Basis:100 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
15.00
75.00
Brick
270.000
no.
15.00
4050.00
Sub-Total(A1)
4125.00
135.34
L7.Labour-Road
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick on Edging
100.000
rft
10.00
1000.00
Sub-Total(L7)
1000.00
32.81
Total(1)
168.15
Add over head on Total(1)
5.0 %
8.41
Total(2)
176.56
Add Profit on Total(2)
10.0 %
17.66
Total(3)
194.21
Add VAT on Unit Price
5.5 %
11.93
Add Income Tax on Unit Price
5.0 %
10.85
Unit Price
217.00
Say
217
per RM