BREAKDOWN OF UNIT PRICE
Item: (A03N6) Brick Bond Con(1:2:4),NCF-138,Brk
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
206.475
no.
15.00
3097.13
Sand - Local
9.924
cft
35.00
347.34
Cement
8.439
bag
535.00
4514.87
Sand - Sylhet
9.924
cft
65.00
645.06
Brick-chips-20mm
39.695
cft
175.00
6946.63
Sub-Total(A1)
15551.02
1673.91
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
44.106
cft
4.00
176.42
Sub-Total(E1)
176.42
18.99
Total(1)
1692.90
Add over head on Total(1)
5.0 %
84.65
Total(2)
1777.55
Add Profit on Total(2)
10.0 %
177.75
Total(3)
1955.30
Add VAT on Unit Price
5.5 %
120.16
Add Income Tax on Unit Price
5.0 %
109.23
Unit Price
2184.69
Say
2185
per m2