BREAKDOWN OF UNIT PRICE
Item: (A03G6) DPC (1:2.5:3),SylSand-75mm
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
5.280
bag
535.00
2824.80
Sand - Sylhet
10.320
cft
65.00
670.80
Stone-chips-19mm
20.640
cft
190.00
3921.60
Sub-Total(A1)
7417.20
798.39
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
25.000
cft
4.00
100.00
Sub-Total(E1)
100.00
10.76
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work-Substructure
50.000
sft
40.00
2000.00
DPC work
100.000
sft
5.00
500.00
Sub-Total(L1)
2500.00
269.10
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
50.000
sft
35.00
1750.00
Bituminous coating
100.000
sft
10.00
1000.00
Sub-Total(M1)
2750.00
296.01
Total(1)
1374.26
Add over head on Total(1)
5.0 %
68.71
Total(2)
1442.97
Add Profit on Total(2)
10.0 %
144.30
Total(3)
1587.27
Add VAT on Unit Price
5.5 %
97.54
Add Income Tax on Unit Price
5.0 %
88.67
Unit Price
1773.49
Say
1773
per SQM