BREAKDOWN OF UNIT PRICE
Item: (A03FY) CC Block-500x500x500 Dump>200m
Basis:4 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Unskilled Labour
0.650
no
600.00
390.00
Sub-Total(L1)
390.00
3120.27
Total(1)
3120.27
Add over head on Total(1)
5.0 %
156.01
Total(2)
3276.28
Add Profit on Total(2)
10.0 %
327.63
Total(3)
3603.91
Add VAT on Unit Price
5.5 %
221.47
Add Income Tax on Unit Price
5.0 %
201.34
Unit Price
4026.71
Say
4027
per m3