BREAKDOWN OF UNIT PRICE
Item: (A02Q1) Padestal Top Finishing
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.300
cft
35.00
10.50
Cement
0.100
bag
535.00
53.50
Sub-Total(A1)
64.00
64.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
0.500
no
800.00
400.00
Sub-Total(L1)
400.00
400.00
Total(1)
464.00
Add over head on Total(1)
5.0 %
23.20
Total(2)
487.20
Add Profit on Total(2)
10.0 %
48.72
Total(3)
535.92
Add VAT on Unit Price
5.5 %
32.93
Add Income Tax on Unit Price
5.0 %
29.94
Unit Price
598.79
Say
599
per NOS