BREAKDOWN OF UNIT PRICE
Item: (A02N2) Riprap-Stone-100mm
Basis:100 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sub-base Work/Gravel fiil
33.000
cft
20.00
660.00
Sub-Total(L1)
660.00
71.04
Total(1)
71.04
Add over head on Total(1)
5.0 %
3.55
Total(2)
74.59
Add Profit on Total(2)
10.0 %
7.46
Total(3)
82.05
Add VAT on Unit Price
5.5 %
5.04
Add Income Tax on Unit Price
5.0 %
4.58
Unit Price
91.68
Say
92
per M2