BREAKDOWN OF UNIT PRICE
Item: (A02N1) Grass Lined Ditch-300x600
Basis:15 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
6.357
cft
12.00
76.28
Levelling, Dressing
14.870
sft
1.00
14.87
Sub-Total(L1)
91.15
65.98
Total(1)
65.98
Add over head on Total(1)
5.0 %
3.30
Total(2)
69.28
Add Profit on Total(2)
10.0 %
6.93
Total(3)
76.21
Add VAT on Unit Price
5.5 %
4.68
Add Income Tax on Unit Price
5.0 %
4.26
Unit Price
85.15
Say
85
per M2