BREAKDOWN OF UNIT PRICE
Item: (A02E) Polythene-Double Layer
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene
3.000
kg
105.00
315.00
Sub-Total(A1)
315.00
33.91
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene laying
200.000
sft
0.25
50.00
Sub-Total(L1)
50.00
5.38
Total(1)
39.29
Add over head on Total(1)
5.0 %
1.96
Total(2)
41.25
Add Profit on Total(2)
10.0 %
4.13
Total(3)
45.38
Add VAT on Unit Price
5.5 %
2.79
Add Income Tax on Unit Price
5.0 %
2.54
Unit Price
50.70
Say
51
per M2