BREAKDOWN OF UNIT PRICE
Item: (A02D) Polythene-Single Layer
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene
1.500
kg
105.00
157.50
Sub-Total(A1)
157.50
16.95
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Polythene laying
100.000
sft
0.25
25.00
Sub-Total(L1)
25.00
2.69
Total(1)
19.64
Add over head on Total(1)
5.0 %
0.98
Total(2)
20.63
Add Profit on Total(2)
10.0 %
2.06
Total(3)
22.69
Add VAT on Unit Price
5.5 %
1.39
Add Income Tax on Unit Price
5.0 %
1.27
Unit Price
25.35
Say
25
per M2