Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (A01D4) RCC Palasiding-1050x600x75
Basis:3 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.871
cft
35.00
30.49
Cement
0.892
bag
535.00
477.22
Sand - Sylhet
0.871
cft
65.00
56.62
Brick-chips-20mm
3.485
cft
175.00
609.88
Sub-Total(A1)
1174.20
1284.18
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
4.052
cft
4.00
16.21
Sub-Total(E1)
16.21
17.73
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
4.052
cft
40.00
162.08
Form work-Substructure
13.966
sft
40.00
558.64
Palasiding-1050x600, 3m
3.000
rft
30.00
90.00
Sub-Total(L1)
810.72
886.66
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Forms-Rect-
13.966
sft
50.00
698.30
Nut Bolt-use 30 time
1.000
kg
4.50
4.50
Sub-Total(M1)
702.80
768.63
Total(1)
2957.19
Add over head on Total(1)
5.0 %
147.86
Total(2)
3105.05
Add Profit on Total(2)
10.0 %
310.50
Total(3)
3415.55
Add VAT on Unit Price
5.5 %
209.89
Add Income Tax on Unit Price
5.0 %
190.81
Unit Price
3816.26
Say
3816
per m