BREAKDOWN OF UNIT PRICE
Item: (A01B1) Excavation below 1.5m, 300m above
Basis:100 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
100.000
cft
12.00
1200.00
Extra earth 0.5m exc 1.5m
100.000
cft
5.00
500.00
Earth Carrying-300m+
100.000
cft
12.00
1200.00
Sub-Total(L1)
2900.00
1024.14
Total(1)
1024.14
Add over head on Total(1)
5.0 %
51.21
Total(2)
1075.34
Add Profit on Total(2)
10.0 %
107.53
Total(3)
1182.88
Add VAT on Unit Price
5.5 %
72.69
Add Income Tax on Unit Price
5.0 %
66.08
Unit Price
1321.65
Say
1322
per CUM