BREAKDOWN OF UNIT PRICE
Item: (A01B0) Excavation below 1.5m, 200-300m
Basis:100 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
100.000
cft
12.00
1200.00
Extra earth 0.5m exc 1.5m
100.000
cft
5.00
500.00
Earth Carrying -200-300m
100.000
cft
9.00
900.00
Sub-Total(L1)
2600.00
918.19
Total(1)
918.19
Add over head on Total(1)
5.0 %
45.91
Total(2)
964.10
Add Profit on Total(2)
10.0 %
96.41
Total(3)
1060.51
Add VAT on Unit Price
5.5 %
65.17
Add Income Tax on Unit Price
5.0 %
59.25
Unit Price
1184.93
Say
1185
per CUM