BREAKDOWN OF UNIT PRICE
Item: (A01AG) Excavation and Back Filling
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mini Roller/ Plate Compac
1.000
cft
4.00
4.00
Sub-Total(E1)
4.00
1.41
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
100.000
cft
12.00
1200.00
Filling
100.000
cft
6.00
600.00
Sub-Total(L1)
1800.00
635.67
Total(1)
637.08
Add over head on Total(1)
5.0 %
31.85
Total(2)
668.94
Add Profit on Total(2)
10.0 %
66.89
Total(3)
735.83
Add VAT on Unit Price
5.5 %
45.22
Add Income Tax on Unit Price
5.0 %
41.11
Unit Price
822.16
Say
822
per Cum