BREAKDOWN OF UNIT PRICE
Item: (A01AE) Earth Excavation-3-6m
Basis:1000 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
1000.000
cft
12.00
12000.00
Extra earth 0.5m exc 1.5m
3000.000
cft
5.00
15000.00
Sub-Total(L1)
27000.00
953.51
Total(1)
953.51
Add over head on Total(1)
5.0 %
47.68
Total(2)
1001.18
Add Profit on Total(2)
10.0 %
100.12
Total(3)
1101.30
Add VAT on Unit Price
5.5 %
67.68
Add Income Tax on Unit Price
5.0 %
61.53
Unit Price
1230.50
Say
1231
per Cum