BREAKDOWN OF UNIT PRICE
Item: (A01AB) Excavation upto 3m 60 m lead
Basis:1000 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Exacavat upto 3m 6m lead
1000.000
cft
7.50
7500.00
Sub-Total(L1)
7500.00
264.86
Total(1)
264.86
Add over head on Total(1)
5.0 %
13.24
Total(2)
278.11
Add Profit on Total(2)
10.0 %
27.81
Total(3)
305.92
Add VAT on Unit Price
5.5 %
18.80
Add Income Tax on Unit Price
5.0 %
17.09
Unit Price
341.81
Say
342
per Cum