Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (A00D8) Pond Cutting
Basis:100 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
100.000
cft
12.00
1200.00
Sub-Total(L1)
1200.00
423.78
Total(1)
423.78
Add over head on Total(1)
5.0 %
21.19
Total(2)
444.97
Add Profit on Total(2)
10.0 %
44.50
Total(3)
489.47
Add VAT on Unit Price
5.5 %
30.08
Add Income Tax on Unit Price
5.0 %
27.34
Unit Price
546.89
Say
547
per M3