BREAKDOWN OF UNIT PRICE
Item: (A00D5) Filling with Borrowed Soil
Basis:100 cft
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavator
0.070
day
10000.00
700.00
Roller hire ch. i/c fuel
0.030
day
15000.00
450.00
Sub-Total(E1)
1150.00
406.12
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling
100.000
cft
6.00
600.00
Sub-Total(L1)
600.00
211.89
Total(1)
618.01
Add over head on Total(1)
5.0 %
30.90
Total(2)
648.91
Add Profit on Total(2)
10.0 %
64.89
Total(3)
713.80
Add VAT on Unit Price
5.5 %
43.87
Add Income Tax on Unit Price
5.0 %
39.88
Unit Price
797.55
Say
798
per M3