BREAKDOWN OF UNIT PRICE
Item: (A00D1) Demolition and Repair-HBB
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
5.000
cft
15.00
75.00
Sub-Total(A1)
75.00
8.07
Total(1)
8.07
Add over head on Total(1)
5.0 %
0.40
Total(2)
8.48
Add Profit on Total(2)
10.0 %
0.85
Total(3)
9.32
Add VAT on Unit Price
5.5 %
0.57
Add Income Tax on Unit Price
5.0 %
0.52
Unit Price
10.42
Say
10
per M2