BREAKDOWN OF UNIT PRICE
Item: (A001D) Mobilization-Site Office-45m2
Basis:1 no.
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Site Office/ Storage
500.000
sft
100.00
50000.00
Toilet Facility
1.000
LS
10000.00
10000.00
Electricity
1.000
LS
7500.00
7500.00
Sub-Total(S1)
67500.00
67500.00
Total(1)
67500.00
Add over head on Total(1)
5.0 %
3375.00
Total(2)
70875.00
Add Profit on Total(2)
10.0 %
7087.50
Total(3)
77962.50
Add VAT on Unit Price
5.5 %
4790.99
Add Income Tax on Unit Price
5.0 %
4355.45
Unit Price
87108.94
Say
87109
per each