Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (A001A) Mobilization of All
Basis:1 no.
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Site Office/ Storage
800.000
sft
100.00
80000.00
Sub-Total(S1)
80000.00
80000.00
Total(1)
80000.00
Add over head on Total(1)
5.0 %
4000.00
Total(2)
84000.00
Add Profit on Total(2)
10.0 %
8400.00
Total(3)
92400.00
Add VAT on Unit Price
5.5 %
5678.21
Add Income Tax on Unit Price
5.0 %
5162.01
Unit Price
103240.22
Say
103240
per LS