BREAKDOWN OF UNIT PRICE
Item: (A001) Mobilization- per Sqm
Basis:2352 sft
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Site Office/ Storage
40.000
sft
100.00
4000.00
Sub-Total(S1)
4000.00
18.31
Total(1)
18.31
Add over head on Total(1)
5.0 %
0.92
Total(2)
19.22
Add Profit on Total(2)
10.0 %
1.92
Total(3)
21.14
Add VAT on Unit Price
5.5 %
1.30
Add Income Tax on Unit Price
5.0 %
1.18
Unit Price
23.62
Say
24
per SQM