BREAKDOWN OF UNIT PRICE
Item: (E03A3) Plaster-upto 5th Floor
Basis:100 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
1.000
bag
375.00
375.00
Local Sand (FM=1.2)
10.000
cft
18.00
180.00
Sub-Total(A1)
555.00
59.74
B5.Labour Finishing
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastering
100.000
sft
9.00
900.00
RCC Chipping
50.000
sft
8.00
400.00
Sub-Total(B5)
1300.00
139.93
D4.Others-Finishing
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-2
100.000
sft
9.00
900.00
Sub-Total(D4)
900.00
96.88
Total(1)
296.55
Add over head on Total(1)
5.0 %
14.83
Total(2)
311.38
Add Profit on Total(2)
10.0 %
31.14
Total(3)
342.51
Add VAT on Unit Price
5.5 %
21.05
Add Income Tax on Unit Price
5.0 %
19.13
Unit Price
382.70
Say
383
per Sqm