BREAKDOWN OF UNIT PRICE
Item: (E02D1) Concrete Block Work-200mm Thick
Basis:100 sft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
0.850
bag
375.00
318.75
Local Sand (FM=1.2)
7.000
cft
18.00
126.00
ConcreteBlock-390x190x190
116.000
no.
66.00
7656.00
Sub-Total(A1)
8100.75
871.96
B5.Labour Finishing
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Blockwork-200mm-10th-11th
100.000
sft
55.00
5500.00
Sub-Total(B5)
5500.00
592.02
Total(1)
1463.98
Add over head on Total(1)
5.0 %
73.20
Total(2)
1537.18
Add Profit on Total(2)
10.0 %
153.72
Total(3)
1690.90
Add VAT on Unit Price
5.5 %
103.91
Add Income Tax on Unit Price
5.0 %
94.46
Unit Price
1889.28
Say
1889
per Sqm