BREAKDOWN OF UNIT PRICE
Item: (C01U3) Concrete-4500psi-18th Floor
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-4500ps
100.000
cft
280.00
28000.00
Sub-Total(A1)
28000.00
9888.20
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 18th Floor
84.118
sft
380.00
31964.84
Sub-Total(B4)
31964.84
11288.38
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
1800.000
cft
0.75
1350.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
2450.00
865.22
Total(1)
22041.80
Add over head on Total(1)
5.0 %
1102.09
Total(2)
23143.89
Add Profit on Total(2)
10.0 %
2314.39
Total(3)
25458.28
Add VAT on Unit Price
5.5 %
1564.48
Add Income Tax on Unit Price
5.0 %
1422.25
Unit Price
28445.01
Say
28445
per Cum