BREAKDOWN OF UNIT PRICE
Item: (C01R1) Concrete-30Mpa-Wal/Col-GF-4th Flr
Basis:100 cft
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready-mix Concrete-GF-4th
100.000
cft
50.00
5000.00
Sub-Total(B4)
5000.00
1765.75
D3.Shuttering-Hardware
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 40 times
3.300
set
15.00
49.50
Sub-Total(D3)
49.50
17.48
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Vibrator
100.000
cft
5.00
500.00
Conrete Pump-GF-4th Floor
100.000
cft
10.00
1000.00
Sub-Total(E1)
1500.00
529.73
Total(1)
2312.96
Add over head on Total(1)
5.0 %
115.65
Total(2)
2428.60
Add Profit on Total(2)
10.0 %
242.86
Total(3)
2671.46
Add VAT on Unit Price
5.5 %
164.17
Add Income Tax on Unit Price
5.0 %
149.24
Unit Price
2984.88
Say
2985
per Cum