BREAKDOWN OF UNIT PRICE
Item: (C01M1) Concrete-4500psi-11th Floor
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-4500ps
100.000
cft
280.00
28000.00
Sub-Total(A1)
28000.00
9888.20
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 11th Floor
86.455
sft
168.95
14606.57
Sub-Total(B4)
14606.57
5158.31
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
1100.000
cft
0.75
825.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
1925.00
679.81
Total(1)
15726.32
Add over head on Total(1)
5.0 %
786.32
Total(2)
16512.64
Add Profit on Total(2)
10.0 %
1651.26
Total(3)
18163.91
Add VAT on Unit Price
5.5 %
1116.22
Add Income Tax on Unit Price
5.0 %
1014.74
Unit Price
20294.87
Say
20295
per cum