BREAKDOWN OF UNIT PRICE
Item: (C01F2) Concrete-3500psi-5th Floor Roof
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-3500ps
100.000
cft
250.00
25000.00
Sub-Total(A1)
25000.00
8828.75
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 5th Floor
86.455
sft
136.25
11779.49
Sub-Total(B4)
11779.49
4159.93
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
600.000
cft
0.75
450.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
1550.00
547.38
Total(1)
13536.06
Add over head on Total(1)
5.0 %
676.80
Total(2)
14212.86
Add Profit on Total(2)
10.0 %
1421.29
Total(3)
15634.15
Add VAT on Unit Price
5.5 %
960.76
Add Income Tax on Unit Price
5.0 %
873.42
Unit Price
17468.32
Say
17468
per cum